Plan reference: plan/glamsterdam-2026-09-05/issues/08-phase-8-network-soak-and-observability.md · Issue 8.8
Description
Run rs-vc across the Gloas activation epoch on the first public network that schedules it, collecting the daily snapshot from 8.7 and triaging every failed gate.
Implementation Notes
- Entry is a network config carrying a real
GLOAS_FORK_EPOCH — read fork epochs, versions and every *_DUE_BPS* from that network's config file at run time; assume no value and no date. Scheduling is the gate; a calendar target never is.
- Run at least one day pre-activation, the boundary itself, and ≥ 14 consecutive days after; the window resets on a configuration change or a redeploy.
- Record each day's snapshot plus every fail-closed rejection (signer type/version, BN capability drop, PTC 204 bursts) with its triage verdict.
- Points cover setup, daily checks and the write-up; the 14 days are elapsed time. If a gate fails, the fix is a new issue in the owning phase, not scope creep here — and a fix that changes the deployed build restarts the 14-day window on the new build (D26); the soak describes one build only, the one 8.9b passed.
Acceptance Criteria
Testing Notes
local keys first, then the remote-signer / DVT cluster; the network's own config files are the source of truth for epochs and deadlines.
Points: 3 · Type: chore · Priority: P0 · Scope: 1.5 days of effort across ≥ 14 elapsed days · Blocked by: #338, #341 (L1–L5 all green at the network's tag, D26) · Blocks: #342
Plan reference:
plan/glamsterdam-2026-09-05/issues/08-phase-8-network-soak-and-observability.md· Issue 8.8Description
Run rs-vc across the Gloas activation epoch on the first public network that schedules it, collecting the daily snapshot from 8.7 and triaging every failed gate.
Implementation Notes
GLOAS_FORK_EPOCH— read fork epochs, versions and every*_DUE_BPS*from that network's config file at run time; assume no value and no date. Scheduling is the gate; a calendar target never is.Acceptance Criteria
rvc_validators_slashed_totalunchanged and noresult="blocked"increment attributable to rs-vc.Testing Notes
local keys first, then the remote-signer / DVT cluster; the network's own config files are the source of truth for epochs and deadlines.
Points: 3 · Type: chore · Priority: P0 · Scope: 1.5 days of effort across ≥ 14 elapsed days · Blocked by: #338, #341 (L1–L5 all green at the network's tag, D26) · Blocks: #342