Plan reference: plan/glamsterdam-2026-09-05/issues/08-phase-8-network-soak-and-observability.md · Issue 8.9b
Description
Triage every root that moved at the new tag and run all five KAT layers to a verdict. The verdict is binary: all green names the exact build 8.8 will soak; anything else blocks 8.8 until fixed and re-run (D26). The readiness record is 8.10's, after the soak.
Implementation Notes
- Each changed root gets a verdict: spec change (record and re-baseline with the spec citation) or rs-vc defect (issue in the owning phase). Never a silent re-baseline.
- If L1 fails at the new tag, ADR-001 (adopt
libssz =0.3.0) reopens and the ADR-007 hand-roll is the fallback; ADR-007 confines the swap to rvc_gloas::merkle, so container declarations do not move. Stop and raise the reversal rather than absorbing it into this issue's points.
- Write the per-layer results and the commit SHA of the build that passed into the Decision Log; 8.8 soaks that SHA and 8.10 records it. A fix to any layer produces a new SHA and re-runs this issue; the soak (if started) restarts.
- 3 points is the triage-plus-record floor, justified by the unbounded diff surface; it is not a budget for an ADR-001 reversal.
Acceptance Criteria
Testing Notes
re-run the full KAT set on the regenerated vectors; mainnet preset nightly, minimal in CI.
Points: 3 · Type: spike · Priority: P0 · Scope: 1.5 days — unbounded above this if L1 fails (see risks) · Blocked by: #340 · Blocks: #339
Plan reference:
plan/glamsterdam-2026-09-05/issues/08-phase-8-network-soak-and-observability.md· Issue 8.9bDescription
Triage every root that moved at the new tag and run all five KAT layers to a verdict. The verdict is binary: all green names the exact build 8.8 will soak; anything else blocks 8.8 until fixed and re-run (D26). The readiness record is 8.10's, after the soak.
Implementation Notes
libssz =0.3.0) reopens and the ADR-007 hand-roll is the fallback; ADR-007 confines the swap torvc_gloas::merkle, so container declarations do not move. Stop and raise the reversal rather than absorbing it into this issue's points.Acceptance Criteria
plan/glamsterdam-2026-09-05/project-plan.md:129) with its verdict and citation; no root re-baselined without one.kat_policy.rsgreen with zero newEXEMPTIONS.Testing Notes
re-run the full KAT set on the regenerated vectors;
mainnetpreset nightly,minimalin CI.Points: 3 · Type: spike · Priority: P0 · Scope: 1.5 days — unbounded above this if L1 fails (see risks) · Blocked by: #340 · Blocks: #339